Major Rehabilitation Projects
Some pavement sections have fallen below the condition range (PCI falling below 55 for NPIAS AC-surfaced pavements; 55 for non-NPIAS AC-surfaced apron, T-hangar, and helipad pavements; 40 for non-NPIAS AC-surfaced runway and taxiway pavements; and 65 for PCC pavements) where they are eligible to be included in the APPP and should instead be considered for major rehabilitation. The table below provides a list of these pavement sections for FAA consideration for future grants.
| Year | Airport Name | Branch | Section | Work Type | Last Construction Date | Surface Type | Priority | Area (sf) | PCI Before Work | Cost |
|---|---|---|---|---|---|---|---|---|---|---|
| 2027 | Ak-Chin Regional | A01AC | 10 | Major M&R Asphalt Overlay | 1/1/1999 | AC | 14 | 11,920 | 40 | $85,000 |
| 2027 | Ak-Chin Regional | A01AC | 20 | Major M&R Asphalt Overlay | 1/1/2004 | AC | 14 | 33,963 | 50 | $241,000 |
| 2027 | Ak-Chin Regional | A01AC | 30 | Major M&R Asphalt Overlay | 10/4/2012 | AC | 14 | 30,505 | 47 | $217,000 |
| 2027 | Ak-Chin Regional | RW422AC | 10 | Major M&R Asphalt Overlay | 1/1/1999 | AC | 6 | 202,599 | 50 | $1,439,000 |
| 2027 | Ak-Chin Regional | TWA2AC | 10 | Major M&R Asphalt Overlay | 1/1/2005 | AC | 10 | 15,280 | 52 | $109,000 |
| 2027 | Ak-Chin Regional | TWA3AC | 10 | Major M&R Asphalt Reconstruction | 1/1/1999 | AC | 24 | 7,961 | 25 | $86,000 |
| 2027 | Avi Suquilla | A01AS | 20 | Major M&R Asphalt Overlay | 6/3/2002 | AC | 14 | 316,797 | 47 | $2,255,000 |
| 2027 | Avi Suquilla | A01AS | 40 | Major M&R PCC Reconstruction | 1/1/2000 | PCC | 25 | 3,201 | 3 | $110,000 |
| 2027 | Avi Suquilla | TWBAS | 20 | Major M&R Asphalt Overlay | 11/3/2010 | AC | 10 | 118,710 | 53 | $845,000 |
| 2027 | Bagdad | A01BG | 10 | Major M&R Asphalt Overlay | 11/1/2004 | AAC | 14 | 52,500 | 48 | $366,000 |
| 2027 | Bagdad | A02BG | 10 | Major M&R Asphalt Reconstruction | 1/1/1975 | AC | 25 | 8,964 | 27 | $95,000 |
| 2027 | Bagdad | TWABG | 20 | Major M&R Asphalt Reconstruction | 11/1/2004 | AAC | 24 | 3,258 | 24 | $35,000 |
| 2027 | Benson Municipal/Paul Kerchum Field | HP01BN | 30 | Major M&R Asphalt Reconstruction | 4/10/2010 | AC | 27 | 5,985 | 36 | $71,000 |
| 2027 | Benson Municipal/Paul Kerchum Field | HP01BN | 40 | Major M&R PCC Reconstruction | 4/10/2010 | PCC | 27 | 2,500 | 18 | $94,000 |
| 2027 | Bisbee Douglas International | A01BD | 10 | Major M&R PCC Reconstruction | 6/1/1942 | PCC | 25 | 93,600 | 13 | $3,511,000 |
| 2027 | Bisbee Douglas International | A01BD | 20 | Major M&R Asphalt Reconstruction | 6/1/1955 | AC | 25 | 9,461 | 1 | $112,000 |
| 2027 | Bisbee Douglas International | A01BD | 30 | Major M&R Asphalt Reconstruction | 4/5/2000 | AAC | 25 | 42,132 | 21 | $500,000 |
| 2027 | Bisbee Douglas International | A01BD | 40 | Major M&R Asphalt Overlay | 3/3/2010 | APC | 14 | 157,279 | 52 | $1,223,000 |
| 2027 | Bisbee Douglas International | A01BD | 50 | Major M&R PCC Reconstruction | 6/1/1980 | PCC | 12 | 6,930 | 65 | $260,000 |
| 2027 | Bisbee Douglas International | RW1735BD | 10 | Major M&R Asphalt Reconstruction | 1/1/2005 | AAC | 23 | 646,167 | 21 | $7,668,000 |
| 2027 | Bisbee Douglas International | TH01BD | 10 | Major M&R Asphalt Reconstruction | 1/1/1960 | AC | 27 | 22,117 | 0 | $262,000 |
| 2027 | Bisbee Douglas International | TWA3BD | 10 | Major M&R Asphalt Reconstruction | 10/3/2005 | AC | 24 | 50,634 | 31 | $601,000 |
| 2027 | Bisbee Douglas International | TWA4BD | 10 | Major M&R Asphalt Reconstruction | 10/15/2003 | AAC | 24 | 113,868 | 34 | $1,351,000 |
| 2027 | Bisbee Municipal | A01BM | 10 | Major M&R Asphalt Reconstruction | 6/30/1997 | AC | 25 | 120,532 | 18 | $1,430,000 |
| 2027 | Bisbee Municipal | TWABM | 10 | Major M&R Asphalt Reconstruction | 6/30/1989 | AC | 24 | 238,332 | 10 | $2,828,000 |
| 2027 | Buckeye Municipal | A01BK | 20 | Major M&R Asphalt Reconstruction | 6/3/2007 | AC | 25 | 123,290 | 24 | $1,493,000 |
| 2027 | Buckeye Municipal | A01BK | 30 | Major M&R PCC Reconstruction | 4/12/2000 | PCC | 14 | 1,650 | 42 | $63,000 |
| 2027 | Buckeye Municipal | AHOLDBK | 10 | Major M&R Asphalt Overlay | 6/6/2012 | AC | 14 | 51,086 | 53 | $405,000 |
| 2027 | Buckeye Municipal | HP01BK | 10 | Major M&R PCC Reconstruction | 6/3/2007 | PCC | 27 | 1,945 | 35 | $74,000 |
| 2027 | Buckeye Municipal | TWEBK | 10 | Major M&R Asphalt Reconstruction | 4/12/1986 | AC | 24 | 49,210 | 39 | $596,000 |
| 2027 | Buckeye Municipal | TWHBK | 10 | Major M&R Asphalt Reconstruction | 5/18/1986 | AC | 24 | 5,790 | 20 | $70,000 |
| 2027 | Buckeye Municipal | TWJBK | 10 | Major M&R Asphalt Reconstruction | 6/30/1998 | AC | 24 | 73,226 | 34 | $887,000 |
| 2027 | Casa Grande Municipal | A01CG | 10 | Major M&R Asphalt Reconstruction | 7/19/2003 | AAC | 25 | 227,990 | 38 | $2,471,000 |
| 2027 | Casa Grande Municipal | A01CG | 20 | Major M&R Asphalt Reconstruction | 7/30/2003 | AAC | 25 | 234,636 | 35 | $2,543,000 |
| 2027 | Casa Grande Municipal | A02CG | 10 | Major M&R Asphalt Reconstruction | 10/29/2003 | AAC | 25 | 57,590 | 33 | $624,000 |
| 2027 | Casa Grande Municipal | HP02CG | 10 | Major M&R PCC Reconstruction | 6/1/1990 | PCC | 27 | 4,800 | 26 | $164,000 |
| 2027 | Casa Grande Municipal | RW523CG | 10 | Major M&R Asphalt Overlay | 8/3/2012 | AAC | 6 | 520,000 | 53 | $3,693,000 |
| 2027 | Casa Grande Municipal | TH01CG | 10 | Major M&R Asphalt Reconstruction | 1/1/1990 | AC | 27 | 135,495 | 30 | $1,469,000 |
| 2027 | Casa Grande Municipal | TWECG | 30 | Major M&R Asphalt Reconstruction | 1/2/1968 | AC | 24 | 9,324 | 25 | $101,000 |
| 2027 | Chandler Municipal | A01CH | 10 | Major M&R Asphalt Overlay | 6/30/1995 | AC | 14 | 290,420 | 43 | $2,304,000 |
| 2027 | Chandler Municipal | A01CH | 20 | Major M&R Asphalt Reconstruction | 5/1/2006 | AAC | 25 | 101,529 | 31 | $1,229,000 |
| 2027 | Chandler Municipal | A01CH | 40 | Major M&R Asphalt Overlay | 6/30/1999 | AAC | 14 | 124,138 | 47 | $985,000 |
| 2027 | Chandler Municipal | A01CH | 50 | Major M&R Asphalt Overlay | 1/3/1980 | AC | 14 | 135,831 | 52 | $1,078,000 |
| 2027 | Chandler Municipal | HP02CH | 20 | Major M&R Asphalt Overlay | 6/1/2005 | AC | 22 | 293,316 | 49 | $2,327,000 |
| 2027 | Chandler Municipal | TH01CH | 10 | Major M&R Asphalt Overlay | 5/1/2006 | AAC | 22 | 505,356 | 55 | $4,009,000 |
| 2027 | Chandler Municipal | TWCCH | 20 | Major M&R Asphalt Reconstruction | 6/30/1992 | AC | 24 | 29,140 | 32 | $353,000 |
| 2027 | Chinle Municipal | A01CN | 10 | Major M&R Asphalt Reconstruction | 1/1/2005 | AC | 25 | 67,500 | 16 | $876,000 |
| 2027 | Chinle Municipal | TWACN | 10 | Major M&R Asphalt Reconstruction | 1/1/2005 | AC | 24 | 17,945 | 23 | $233,000 |
| 2027 | Chinle Municipal | TWACN | 20 | Major M&R Asphalt Reconstruction | 1/1/2005 | AC | 24 | 21,777 | 23 | $283,000 |
| 2027 | Chinle Municipal | TWACN | 30 | Major M&R Asphalt Reconstruction | 1/1/2005 | AC | 24 | 9,793 | 1 | $127,000 |
| 2027 | Cochise College | A01CC | 10 | Major M&R Asphalt Reconstruction | 6/30/1989 | AC | 25 | 177,656 | 15 | $2,108,000 |
| 2027 | Cochise College | A01CC | 20 | Major M&R Asphalt Reconstruction | 6/30/1991 | AC | 25 | 124,506 | 30 | $1,477,000 |
| 2027 | Cochise College | A01CC | 30 | Major M&R PCC Reconstruction | 1/1/1996 | PCC | 25 | 1,202 | 14 | $45,000 |
| 2027 | Cochise College | TWACC | 10 | Major M&R Asphalt Reconstruction | 6/29/1984 | AC | 24 | 26,908 | 0 | $319,000 |
| 2027 | Cochise County | TWA1CO | 10 | Major M&R Asphalt Overlay | 8/3/2001 | AC | 10 | 8,223 | 55 | $64,000 |
| 2027 | Cochise County | TWACO | 10 | Major M&R Asphalt Overlay | 6/3/2008 | AC | 10 | 100,650 | 48 | $782,000 |
| 2027 | Colorado City Municipal | TH01CL | 10 | Major M&R Asphalt Reconstruction | 6/1/1993 | AC | 27 | 31,077 | 24 | $381,000 |
| 2027 | Colorado City Municipal | TH01CL | 20 | Major M&R Asphalt Overlay | 1/1/2004 | AAC | 22 | 14,507 | 52 | $117,000 |
| 2027 | Colorado City Municipal | TWBCL | 20 | Major M&R Asphalt Reconstruction | 1/1/1999 | AC | 24 | 4,083 | 40 | $50,000 |
| 2027 | Coolidge Municipal | A01CM | 10 | Major M&R PCC Reconstruction | 6/1/1986 | PCC | 25 | 453,404 | 18 | $15,534,000 |
| 2027 | Coolidge Municipal | RW1735CM | 10 | Major M&R Asphalt Overlay | 3/4/2014 | AAC | 18 | 276,455 | 53 | $1,963,000 |
| 2027 | Coolidge Municipal | TH01CM | 10 | Major M&R Asphalt Overlay | 6/1/2005 | AC | 22 | 26,788 | 43 | $190,000 |
| 2027 | Coolidge Municipal | TH01CM | 30 | Major M&R Asphalt Overlay | 2/1/2015 | AC | 22 | 15,558 | 48 | $110,000 |
| 2027 | Coolidge Municipal | TWACM | 10 | Major M&R Asphalt Overlay | 2/4/2014 | AAC | 10 | 209,965 | 47 | $1,491,000 |
| 2027 | Coolidge Municipal | TWBCM | 10 | Major M&R Asphalt Overlay | 1/1/1984 | AC | 10 | 34,625 | 46 | $246,000 |
| 2027 | Cottonwood | TWACT | 10 | Major M&R Asphalt Overlay | 6/3/1986 | AC | 10 | 142,552 | 49 | $994,000 |
| 2027 | Douglas Municipal | A01DM | 10 | Major M&R Asphalt Reconstruction | 12/17/2004 | AAC | 25 | 137,467 | 21 | $1,631,000 |
| 2027 | Douglas Municipal | A02DM | 10 | Major M&R Asphalt Reconstruction | 6/30/1992 | AC | 25 | 322,231 | 40 | $3,824,000 |
| 2027 | Eloy Municipal | A01EM | 10 | Major M&R Asphalt Reconstruction | 6/2/2012 | AAC | 25 | 86,862 | 36 | $941,000 |
| 2027 | Eloy Municipal | TH01EM | 20 | Major M&R Asphalt Reconstruction | 6/1/2001 | AC | 27 | 11,581 | 20 | $126,000 |
| 2027 | Eloy Municipal | TWAEM | 15 | Major M&R Asphalt Overlay | 11/18/2004 | AAC | 10 | 12,862 | 46 | $91,000 |
| 2027 | Eric Marcus Municipal | A01AJ | 10 | Major M&R PCC Reconstruction | 1/1/1950 | PCC | 25 | 754,974 | 29 | $22,976,000 |
| 2027 | Eric Marcus Municipal | TWAAJ | 10 | Major M&R Asphalt Reconstruction | 1/3/2012 | AAC | 24 | 25,914 | 40 | $249,000 |
| 2027 | Falcon Field | AECHOMF | 10 | Major M&R Asphalt Overlay | 7/1/2006 | AAC | 14 | 230,825 | 52 | $1,831,000 |
| 2027 | Falcon Field | AECHOMF | 20 | Major M&R Asphalt Overlay | 6/3/2008 | AC | 14 | 188,125 | 41 | $1,492,000 |
| 2027 | Falcon Field | AFALCONMF | 10 | Major M&R Asphalt Reconstruction | 1/1/1991 | AC | 25 | 84,583 | 24 | $1,024,000 |
| 2027 | Falcon Field | AFALCONMF | 30 | Major M&R Asphalt Overlay | 6/3/2009 | AC | 14 | 62,493 | 45 | $496,000 |
| 2027 | Falcon Field | AFALCONMF | 40 | Major M&R Asphalt Overlay | 8/1/2006 | AC | 14 | 16,336 | 49 | $130,000 |
| 2027 | Falcon Field | AFALCONMF | 50 | Major M&R Asphalt Overlay | 6/2/2012 | AC | 14 | 551,009 | 47 | $4,371,000 |
| 2027 | Falcon Field | AFALCONMF | 60 | Major M&R Asphalt Overlay | 12/2/2014 | AAC | 14 | 201,834 | 49 | $1,601,000 |
| 2027 | Falcon Field | AFALCONMF | 70 | Major M&R Asphalt Overlay | 12/3/2014 | AC | 14 | 241,101 | 51 | $1,913,000 |
| 2027 | Falcon Field | AHIGLEYMF | 5 | Major M&R Asphalt Reconstruction | 1/1/1991 | AC | 25 | 6,388 | 31 | $77,000 |
| 2027 | Falcon Field | AHIGLEYMF | 15 | Major M&R Asphalt Overlay | 6/30/2001 | AC | 14 | 5,395 | 51 | $43,000 |
| 2027 | Falcon Field | TH01MF | 20 | Major M&R Asphalt Reconstruction | 1/2/2003 | AC | 27 | 571,399 | 40 | $6,918,000 |
| 2027 | Falcon Field | TH01MF | 30 | Major M&R Asphalt Overlay | 2/15/2000 | AC | 22 | 86,023 | 47 | $682,000 |
| 2027 | Falcon Field | TH01MF | 40 | Major M&R Asphalt Overlay | 12/2/2014 | AAC | 22 | 257,007 | 50 | $2,039,000 |
| 2027 | Falcon Field | TWANZIOMF | 10 | Major M&R Asphalt Overlay | 6/1/1992 | AC | 10 | 33,196 | 45 | $263,000 |
| 2027 | Falcon Field | TWBMF | 10 | Major M&R Asphalt Reconstruction | 7/1/2006 | AAC | 24 | 164,650 | 34 | $1,994,000 |
| 2027 | Falcon Field | TWEMF | 10 | Major M&R Asphalt Reconstruction | 7/1/2006 | AAC | 24 | 253,464 | 40 | $3,069,000 |
| 2027 | Flagstaff Pulliam | TWAFG | 30 | Major M&R Asphalt Reconstruction | 11/3/2007 | AC | 24 | 104,604 | 32 | $1,224,000 |
| 2027 | Flagstaff Pulliam | TWWFG | 10 | Major M&R Asphalt Reconstruction | 9/16/2003 | AAC | 24 | 214,413 | 15 | $2,510,000 |
| 2027 | Gila Bend Municipal | A01GB | 10 | Major M&R Asphalt Overlay | 11/3/2014 | AAC | 14 | 132,818 | 49 | $1,054,000 |
| 2027 | Gila Bend Municipal | A01GB | 20 | Major M&R PCC Reconstruction | 11/1/2002 | PCC | 14 | 33,994 | 52 | $1,301,000 |
| 2027 | Gila Bend Municipal | RW422GB | 10 | Major M&R Asphalt Reconstruction | 10/4/2012 | AAC | 23 | 390,850 | 32 | $4,732,000 |
| 2027 | Glendale Regional | A01GL | 10 | Major M&R Asphalt Overlay | 6/30/1993 | AC | 14 | 38,549 | 49 | $306,000 |
| 2027 | Glendale Regional | A01GL | 20 | Major M&R Asphalt Reconstruction | 1/1/1986 | AC | 25 | 373,563 | 25 | $4,523,000 |
| 2027 | Glendale Regional | HP01GL | 10 | Major M&R PCC Reconstruction | 7/1/1986 | PCC | 27 | 4,356 | 2 | $167,000 |
| 2027 | Glendale Regional | RW119GL | 10 | Major M&R Asphalt Overlay | 10/15/2003 | AAC | 6 | 716,079 | 53 | $5,681,000 |
| 2027 | Glendale Regional | TH01GL | 20 | Major M&R Asphalt Reconstruction | 6/30/1986 | AC | 27 | 350,035 | 39 | $4,238,000 |
| 2027 | Grand Canyon National Park | A01GC | 40 | Major M&R Asphalt Overlay | 6/1/1998 | AC | 14 | 145,209 | 54 | $1,114,000 |
| 2027 | Grand Canyon National Park | TWPGC | 10 | Major M&R Asphalt Overlay | 1/1/1997 | AAC | 10 | 382,734 | 46 | $2,935,000 |
| 2027 | Grand Canyon West | HP01PS | 30 | Major M&R PCC Reconstruction | 10/3/2010 | PCC | 27 | 4,800 | 5 | $186,000 |
| 2027 | Greenlee County | A01GR | 10 | Major M&R PCC Reconstruction | 6/30/1982 | PCC | 25 | 65,186 | 33 | $2,615,000 |
| 2027 | Greenlee County | RW725GR | 10 | Major M&R Asphalt Overlay | 6/4/2014 | AAC | 6 | 373,275 | 46 | $3,104,000 |
| 2027 | Greenlee County | TWAGR | 10 | Major M&R Asphalt Overlay | 3/17/2005 | AC | 10 | 76,967 | 44 | $640,000 |
| 2027 | Holbrook Municipal | TWAHL | 10 | Major M&R Asphalt Overlay | 7/2/2015 | AAC | 10 | 234,387 | 48 | $1,481,000 |
| 2027 | Kayenta | A01KY | 10 | Major M&R Asphalt Reconstruction | 1/1/1990 | AC | 25 | 35,896 | 18 | $346,000 |
| 2027 | Kayenta | A02KY | 10 | Major M&R Asphalt Overlay | 6/1/2008 | AC | 14 | 72,250 | 51 | $457,000 |
| 2027 | Kayenta | TWAKY | 10 | Major M&R Asphalt Overlay | 6/1/2008 | AC | 10 | 41,128 | 46 | $260,000 |
| 2027 | Kayenta | TWAKY | 20 | Major M&R Asphalt Reconstruction | 6/1/2008 | AC | 24 | 23,730 | 28 | $229,000 |
| 2027 | Kayenta | TWAKY | 30 | Major M&R Asphalt Reconstruction | 6/1/2008 | AC | 24 | 13,716 | 39 | $132,000 |
| 2027 | Kearny | A01KE | 10 | Major M&R Asphalt Reconstruction | 6/3/1998 | AC | 25 | 48,785 | 32 | $529,000 |
| 2027 | Kearny | RW826KE | 10 | Major M&R PCC Reconstruction | 6/1/1998 | PCC | 23 | 233,467 | 33 | $7,999,000 |
| 2027 | Kingman | A01KG | 10 | Major M&R Asphalt Overlay | 12/3/2009 | AC | 14 | 986,450 | 54 | $7,923,000 |
| 2027 | Kingman | A01KG | 20 | Major M&R Asphalt Overlay | 11/2/2004 | AC | 14 | 225,950 | 50 | $1,815,000 |
| 2027 | Kingman | A01KG | 30 | Major M&R PCC Reconstruction | 6/1/1940 | PCC | 25 | 291,695 | 34 | $11,304,000 |
| 2027 | Kingman | A01KG | 40 | Major M&R PCC Reconstruction | 6/1/1940 | PCC | 25 | 445,405 | 19 | $17,260,000 |
| 2027 | Kingman | A01KG | 45 | Major M&R Asphalt Reconstruction | 6/1/2003 | APC | 25 | 30,375 | 18 | $372,000 |
| 2027 | Kingman | A01KG | 50 | Major M&R Asphalt Reconstruction | 6/1/1940 | AC | 25 | 234,491 | 0 | $2,875,000 |
| 2027 | Kingman | TH01KG | 10 | Major M&R Asphalt Overlay | 6/1/2001 | AC | 22 | 133,045 | 50 | $1,069,000 |
| 2027 | Kingman | TWAKG | 10 | Major M&R Asphalt Reconstruction | 1/1/1991 | AAC | 24 | 144,416 | 39 | $1,770,000 |
| 2027 | Kingman | TWAKG | 20 | Major M&R PCC Reconstruction | 6/1/1940 | PCC | 8 | 108,323 | 57 | $4,198,000 |
| 2027 | Kingman | TWCKG | 5 | Major M&R PCC Reconstruction | 6/1/1940 | PCC | 10 | 14,078 | 50 | $546,000 |
| 2027 | Kingman | TWDKG | 10 | Major M&R Asphalt Reconstruction | 8/2/2014 | APC | 24 | 704,624 | 28 | $8,638,000 |
| 2027 | Lake Havasu City | A01LH | 10 | Major M&R Asphalt Reconstruction | 6/2/1990 | AC | 25 | 880,443 | 37 | $10,793,000 |
| 2027 | Lake Havasu City | A01LH | 20 | Major M&R Asphalt Reconstruction | 6/30/1999 | AAC | 25 | 285,096 | 30 | $3,495,000 |
| 2027 | Lake Havasu City | A02LH | 10 | Major M&R Asphalt Overlay | 6/1/1996 | AC | 14 | 153,484 | 42 | $1,233,000 |
| 2027 | Lake Havasu City | A02LH | 20 | Major M&R Asphalt Reconstruction | 1/12/2003 | AC | 25 | 51,375 | 31 | $630,000 |
| 2027 | Lake Havasu City | TH01LH | 10 | Major M&R Asphalt Overlay | 6/1/1996 | AC | 22 | 229,669 | 43 | $1,845,000 |
| 2027 | Lake Havasu City | TWALH | 20 | Major M&R Asphalt Reconstruction | 6/30/1999 | AAC | 24 | 28,581 | 36 | $350,000 |
| 2027 | Lake Havasu City | TWCLH | 10 | Major M&R Asphalt Overlay | 6/30/1999 | AAC | 10 | 153,606 | 43 | $1,234,000 |
| 2027 | Laughlin/Bullhead International | ASOUTHLB | 10 | Major M&R Asphalt Overlay | 3/1/2016 | AAC | 14 | 143,494 | 49 | $1,153,000 |
| 2027 | Laughlin/Bullhead International | ASOUTHLB | 50 | Major M&R Asphalt Overlay | 3/1/2016 | AAC | 14 | 18,450 | 52 | $148,000 |
| 2027 | Laughlin/Bullhead International | TWA5LB | 10 | Major M&R Asphalt Overlay | 6/3/2009 | AC | 10 | 16,121 | 47 | $129,000 |
| 2027 | Laughlin/Bullhead International | TWALB | 10 | Major M&R Asphalt Overlay | 2/3/2014 | AAC | 10 | 327,017 | 42 | $2,627,000 |
| 2027 | Marana Regional | A02AV | 20 | Major M&R Asphalt Overlay | 1/3/2008 | AC | 14 | 177,158 | 52 | $1,117,000 |
| 2027 | Marana Regional | A03AV | 20 | Major M&R Asphalt Overlay | 11/2/2005 | AC | 14 | 68,653 | 49 | $433,000 |
| 2027 | Marana Regional | TH02AV | 10 | Major M&R Asphalt Overlay | 12/1/2004 | AC | 22 | 476,758 | 46 | $3,007,000 |
| 2027 | Marana Regional | TWAAV | 10 | Major M&R Asphalt Reconstruction | 6/4/2012 | AAC | 24 | 486,900 | 40 | $4,688,000 |
| 2027 | Marana Regional | TWBAV | 10 | Major M&R Asphalt Overlay | 4/3/2016 | AAC | 10 | 89,870 | 54 | $567,000 |
| 2027 | Marana Regional | TWBAV | 25 | Major M&R Asphalt Reconstruction | 1/1/1989 | AC | 24 | 8,904 | 29 | $86,000 |
| 2027 | Marana Regional | TWCAV | 10 | Major M&R Asphalt Reconstruction | 5/17/2006 | AAC | 24 | 112,674 | 30 | $1,085,000 |
| 2027 | Marana Regional | TWEAV | 10 | Major M&R Asphalt Overlay | 11/2/2005 | AC | 10 | 188,199 | 52 | $1,187,000 |
| 2027 | Mesa Gateway | ACESSNAWG | 10 | Major M&R PCC Reconstruction | 6/1/2008 | PCC | 25 | 127,040 | 27 | $4,862,000 |
| 2027 | Mesa Gateway | AHAWKERWG | 10 | Major M&R PCC Reconstruction | 6/1/2008 | PCC | 12 | 54,792 | 56 | $2,097,000 |
| 2027 | Mesa Gateway | AIARWG | 10 | Major M&R PCC Reconstruction | 7/2/1954 | PCC | 12 | 62,183 | 56 | $2,380,000 |
| 2027 | Mesa Gateway | ANORTHWG | 40 | Major M&R PCC Reconstruction | 6/1/1943 | PCC | 25 | 4,625 | 32 | $177,000 |
| 2027 | Mesa Gateway | ARONWG | 10 | Major M&R Asphalt Overlay | 7/2/2012 | AAC | 14 | 148,880 | 44 | $1,181,000 |
| 2027 | Mesa Gateway | ARONWG | 30 | Major M&R Asphalt Overlay | 8/2/2021 | AAC | 14 | 7,863 | 48 | $62,000 |
| 2027 | Mesa Gateway | ASOUTHWG | 10 | Major M&R PCC Reconstruction | 6/1/1975 | PCC | 14 | 44,562 | 47 | $1,706,000 |
| 2027 | Mesa Gateway | TWAWG | 15 | Major M&R PCC Reconstruction | 6/1/1968 | PCC | 8 | 12,192 | 60 | $467,000 |
| 2027 | Mesa Gateway | TWEWG | 20 | Major M&R PCC Reconstruction | 6/1/1987 | PCC | 10 | 16,980 | 41 | $650,000 |
| 2027 | Mesa Gateway | TWGWG | 20 | Major M&R PCC Reconstruction | 6/1/1969 | PCC | 8 | 19,500 | 58 | $746,000 |
| 2027 | Mesa Gateway | TWGWG | 110 | Major M&R PCC Reconstruction | 6/1/1942 | PCC | 24 | 49,584 | 27 | $1,898,000 |
| 2027 | Mesa Gateway | TWGWG | 120 | Major M&R PCC Reconstruction | 6/1/1987 | PCC | 10 | 63,858 | 51 | $2,444,000 |
| 2027 | Mesa Gateway | TWGWG | 130 | Major M&R PCC Reconstruction | 6/1/1942 | PCC | 24 | 52,046 | 34 | $1,992,000 |
| 2027 | Mesa Gateway | TWGWG | 140 | Major M&R PCC Reconstruction | 6/1/1958 | PCC | 24 | 35,187 | 24 | $1,347,000 |
| 2027 | Mesa Gateway | TWKWG | 40 | Major M&R PCC Reconstruction | 6/1/1942 | PCC | 10 | 20,244 | 54 | $775,000 |
| 2027 | Mesa Gateway | TWKWG | 60 | Major M&R PCC Reconstruction | 6/1/1942 | PCC | 10 | 20,255 | 42 | $775,000 |
| 2027 | Mesa Gateway | TWKWG | 70 | Major M&R PCC Reconstruction | 6/1/1958 | PCC | 24 | 17,794 | 25 | $681,000 |
| 2027 | Nogales International | A02NG | 10 | Major M&R PCC Reconstruction | 1/1/2004 | PCC | 25 | 50,683 | 8 | $1,716,000 |
| 2027 | Page Municipal | A01PM | 60 | Major M&R Asphalt Overlay | 1/17/2013 | AC | 14 | 198,510 | 54 | $1,522,000 |
| 2027 | Page Municipal | TH01PM | 10 | Major M&R Asphalt Reconstruction | 6/1/1998 | AC | 27 | 57,414 | 33 | $672,000 |
| 2027 | Page Municipal | TH01PM | 50 | Major M&R Asphalt Overlay | 3/15/2011 | AC | 22 | 85,534 | 51 | $656,000 |
| 2027 | Page Municipal | TWAPM | 10 | Major M&R Asphalt Overlay | 7/1/2006 | AAC | 10 | 275,022 | 45 | $2,109,000 |
| 2027 | Payson | A01PY | 10 | Major M&R Asphalt Reconstruction | 6/30/1990 | AC | 25 | 62,365 | 32 | $733,000 |
| 2027 | Payson | A01PY | 20 | Major M&R Asphalt Reconstruction | 6/30/1981 | AC | 25 | 74,270 | 9 | $873,000 |
| 2027 | Payson | A02PY | 10 | Major M&R Asphalt Overlay | 4/10/1999 | AC | 14 | 93,402 | 40 | $719,000 |
| 2027 | Payson | TWAPY | 10 | Major M&R Asphalt Overlay | 10/4/2003 | AAC | 10 | 211,812 | 44 | $1,631,000 |
| 2027 | Payson | TWFUELPY | 10 | Major M&R Asphalt Overlay | 8/3/2015 | AC | 10 | 14,990 | 44 | $115,000 |
| 2027 | Phoenix Deer Valley | ANWDV | 10 | Major M&R Asphalt Overlay | 12/15/2009 | AC | 14 | 257,575 | 53 | $2,043,000 |
| 2027 | Phoenix Deer Valley | ASRDV | 010 | Major M&R Asphalt Overlay | 11/25/2008 | AC | 14 | 60,170 | 45 | $477,000 |
| 2027 | Phoenix Deer Valley | ASRDV | 040 | Major M&R Asphalt Overlay | 9/4/2009 | AC | 14 | 267,010 | 46 | $2,118,000 |
| 2027 | Phoenix Deer Valley | ASRDV | 050 | Major M&R Asphalt Reconstruction | 3/3/2008 | AC | 25 | 64,442 | 30 | $780,000 |
| 2027 | Phoenix Deer Valley | ASRDV | 060 | Major M&R Asphalt Reconstruction | 6/2/1975 | AC | 25 | 29,501 | 31 | $357,000 |
| 2027 | Phoenix Deer Valley | ASRDV | 070 | Major M&R Asphalt Reconstruction | 6/1/1995 | AC | 25 | 64,202 | 34 | $777,000 |
| 2027 | Phoenix Deer Valley | ASRDV | 080 | Major M&R Asphalt Reconstruction | 1/1/1995 | AC | 25 | 5,382 | 7 | $65,000 |
| 2027 | Phoenix Deer Valley | ASRDV | 090 | Major M&R Asphalt Overlay | 6/1/2018 | AC | 14 | 13,934 | 46 | $111,000 |
| 2027 | Phoenix Deer Valley | ASRDV | 100 | Major M&R Asphalt Reconstruction | 9/4/2014 | AC | 25 | 11,625 | 31 | $141,000 |
| 2027 | Phoenix Deer Valley | ASRDV | 110 | Major M&R Asphalt Overlay | 6/1/2014 | AAC | 14 | 164,746 | 43 | $1,307,000 |
| 2027 | Phoenix Deer Valley | ASRDV | 120 | Major M&R Asphalt Overlay | 6/1/2014 | AAC | 14 | 118,939 | 45 | $944,000 |
| 2027 | Phoenix Deer Valley | ATA13HRDV | 10 | Major M&R Asphalt Reconstruction | 6/2/1995 | AC | 25 | 15,600 | 30 | $189,000 |
| 2027 | Phoenix Deer Valley | ATAHRDV | 10 | Major M&R Asphalt Overlay | 8/3/2014 | AC | 14 | 83,827 | 52 | $665,000 |
| 2027 | Phoenix Deer Valley | RW07LDV | 10 | Major M&R Asphalt Overlay | 11/2/2012 | AAC | 18 | 53,161 | 40 | $422,000 |
| 2027 | Phoenix Deer Valley | RW07LDV | 20 | Major M&R Asphalt Overlay | 11/2/2012 | AAC | 18 | 52,500 | 42 | $417,000 |
| 2027 | Phoenix Deer Valley | RW07LDV | 30 | Major M&R Asphalt Overlay | 11/2/2012 | AAC | 18 | 232,500 | 43 | $1,845,000 |
| 2027 | Phoenix Deer Valley | RW07RDV | 10 | Major M&R Asphalt Overlay | 6/3/2016 | AAC | 6 | 313,453 | 45 | $2,487,000 |
| 2027 | Phoenix Deer Valley | THNEDV | 20 | Major M&R PCC Reconstruction | 4/10/1993 | PCC | 27 | 4,636 | 1 | $177,000 |
| 2027 | Phoenix Deer Valley | THSDV | 10 | Major M&R Asphalt Overlay | 11/25/2008 | AC | 22 | 824,210 | 55 | $6,539,000 |
| 2027 | Phoenix Deer Valley | THSDV | 20 | Major M&R Asphalt Reconstruction | 6/2/1975 | AC | 27 | 67,962 | 16 | $823,000 |
| 2027 | Phoenix Deer Valley | THSDV | 30 | Major M&R Asphalt Reconstruction | 1/9/2008 | AC | 27 | 1,301,829 | 38 | $15,762,000 |
| 2027 | Phoenix Deer Valley | THSDV | 40 | Major M&R Asphalt Reconstruction | 6/1/2008 | AC | 27 | 170,395 | 36 | $2,063,000 |
| 2027 | Phoenix Deer Valley | THSDV | 50 | Major M&R PCC Reconstruction | 4/9/1983 | PCC | 27 | 6,577 | 5 | $252,000 |
| 2027 | Phoenix Deer Valley | TWA04DV | 10 | Major M&R Asphalt Reconstruction | 11/2/2012 | AAC | 24 | 3,407 | 36 | $41,000 |
| 2027 | Phoenix Deer Valley | TWA05DV | 10 | Major M&R Asphalt Reconstruction | 11/2/2012 | AAC | 24 | 3,413 | 32 | $41,000 |
| 2027 | Phoenix Deer Valley | TWADV | 20 | Major M&R Asphalt Overlay | 6/2/1995 | AC | 10 | 29,857 | 46 | $237,000 |
| 2027 | Phoenix Deer Valley | TWADV | 30 | Major M&R Asphalt Reconstruction | 11/2/2012 | AAC | 24 | 8,399 | 29 | $102,000 |
| 2027 | Phoenix Deer Valley | TWC06DV | 10 | Major M&R Asphalt Overlay | 8/10/1999 | AAC | 10 | 9,598 | 43 | $76,000 |
| 2027 | Phoenix Deer Valley | TWC06DV | 20 | Major M&R Asphalt Overlay | 5/3/2015 | AAC | 10 | 4,693 | 51 | $37,000 |
| 2027 | Phoenix Deer Valley | TWCDV | 10 | Major M&R Asphalt Overlay | 5/3/2015 | AAC | 10 | 47,750 | 41 | $379,000 |
| 2027 | Phoenix Deer Valley | TWCDV | 20 | Major M&R Asphalt Overlay | 5/3/2015 | AAC | 10 | 61,820 | 41 | $490,000 |
| 2027 | Phoenix Deer Valley | TWCDV | 30 | Major M&R Asphalt Reconstruction | 5/3/2015 | AAC | 24 | 263,555 | 37 | $3,191,000 |
| 2027 | Phoenix Deer Valley | TWCDV | 40 | Major M&R Asphalt Reconstruction | 8/10/1999 | AAC | 24 | 19,369 | 33 | $235,000 |
| 2027 | Phoenix Deer Valley | TWCDV | 50 | Major M&R Asphalt Overlay | 8/10/1999 | AAC | 10 | 10,480 | 43 | $83,000 |
| 2027 | Phoenix Deer Valley | TWCDV | 60 | Major M&R Asphalt Overlay | 5/3/2015 | AAC | 10 | 4,405 | 44 | $35,000 |
| 2027 | Phoenix Goodyear | ATERMGY | 10 | Major M&R PCC Reconstruction | 6/1/1941 | PCC | 14 | 149,232 | 46 | $5,712,000 |
| 2027 | Phoenix Goodyear | ATERMGY | 20 | Major M&R PCC Reconstruction | 6/1/1941 | PCC | 25 | 209,374 | 26 | $8,013,000 |
| 2027 | Phoenix Goodyear | RW321GY | 020 | Major M&R PCC Reconstruction | 6/1/1996 | PCC | 4 | 49,490 | 63 | $1,894,000 |
| 2027 | Phoenix Goodyear | TH03GY | 10 | Major M&R PCC Reconstruction | 6/1/1941 | PCC | 27 | 81,073 | 0 | $3,103,000 |
| 2027 | Phoenix Goodyear | THNORTHGY | 20 | Major M&R Asphalt Reconstruction | 6/2/1989 | AC | 27 | 144,242 | 39 | $1,746,000 |
| 2027 | Phoenix Goodyear | THNORTHGY | 40 | Major M&R Asphalt Overlay | 6/2/1990 | AC | 22 | 138,015 | 46 | $1,095,000 |
| 2027 | Phoenix Goodyear | TWA2GY | 10 | Major M&R Asphalt Reconstruction | 6/1/1996 | APC | 24 | 4,843 | 35 | $59,000 |
| 2027 | Phoenix Goodyear | TWA2GY | 30 | Major M&R PCC Reconstruction | 6/1/1941 | PCC | 24 | 11,710 | 38 | $448,000 |
| 2027 | Phoenix Goodyear | TWA3GY | 10 | Major M&R Asphalt Overlay | 4/2/2019 | AAC | 10 | 14,812 | 54 | $118,000 |
| 2027 | Phoenix Goodyear | TWTERMGY | 10 | Major M&R PCC Reconstruction | 6/1/1941 | PCC | 24 | 118,594 | 11 | $4,539,000 |
| 2027 | Pinal Airpark | A01PA | 10 | Major M&R PCC Reconstruction | 1/1/1942 | PCC | 25 | 1,512,845 | 8 | $51,832,000 |
| 2027 | Pinal Airpark | TWAPA | 10 | Major M&R Asphalt Overlay | 12/2/2015 | APC | 10 | 483,615 | 53 | $3,434,000 |
| 2027 | Pinal Airpark | TWAPA | 20 | Major M&R Asphalt Reconstruction | 1/1/1970 | AC | 24 | 145,557 | 17 | $1,578,000 |
| 2027 | Polacca | A01PO | 10 | Major M&R Asphalt Overlay | 4/1/2013 | AAC | 14 | 14,193 | 54 | $90,000 |
| 2027 | Polacca | RW422PO | 10 | Major M&R Asphalt Reconstruction | 1/1/1981 | AC | 23 | 221,088 | 0 | $2,133,000 |
| 2027 | Prescott Regional/Ernest A Love Field | ANORTHPR | 10 | Major M&R Asphalt Overlay | 6/1/2000 | AAC | 14 | 256,525 | 50 | $1,789,000 |
| 2027 | Prescott Regional/Ernest A Love Field | ASOUTHPR | 10 | Major M&R Asphalt Overlay | 8/28/2003 | AC | 14 | 61,559 | 54 | $429,000 |
| 2027 | Prescott Regional/Ernest A Love Field | ASOUTHPR | 20 | Major M&R Asphalt Overlay | 1/4/1995 | AC | 14 | 116,369 | 50 | $812,000 |
| 2027 | Prescott Regional/Ernest A Love Field | ASOUTHPR | 30 | Major M&R Asphalt Reconstruction | 1/4/1995 | AC | 25 | 29,938 | 29 | $319,000 |
| 2027 | Prescott Regional/Ernest A Love Field | TH01PR | 10 | Major M&R Asphalt Reconstruction | 6/1/1995 | AC | 27 | 71,422 | 38 | $760,000 |
| 2027 | Prescott Regional/Ernest A Love Field | TH02PR | 10 | Major M&R Asphalt Overlay | 6/1/2002 | AC | 22 | 261,830 | 45 | $1,826,000 |
| 2027 | Prescott Regional/Ernest A Love Field | TH02PR | 20 | Major M&R Asphalt Overlay | 6/1/2002 | AC | 22 | 173,777 | 44 | $1,212,000 |
| 2027 | Prescott Regional/Ernest A Love Field | TWCPR | 20 | Major M&R Asphalt Overlay | 3/4/2013 | AC | 10 | 40,437 | 53 | $282,000 |
| 2027 | Prescott Regional/Ernest A Love Field | TWCPR | 50 | Major M&R Asphalt Reconstruction | 1/1/1998 | AAC | 24 | 18,525 | 33 | $197,000 |
| 2027 | Prescott Regional/Ernest A Love Field | TWCPR | 60 | Major M&R Asphalt Overlay | 6/2/2013 | AAC | 10 | 9,701 | 54 | $68,000 |
| 2027 | Prescott Regional/Ernest A Love Field | TWDPR | 10 | Major M&R Asphalt Overlay | 1/1/1995 | AAC | 10 | 613,018 | 40 | $4,276,000 |
| 2027 | Prescott Regional/Ernest A Love Field | TWDPR | 20 | Major M&R Asphalt Reconstruction | 3/4/2013 | AC | 24 | 99,779 | 32 | $1,062,000 |
| 2027 | Prescott Regional/Ernest A Love Field | TWDPR | 30 | Major M&R Asphalt Overlay | 3/4/2013 | AC | 10 | 70,711 | 53 | $493,000 |
| 2027 | Prescott Regional/Ernest A Love Field | TWFPR | 10 | Major M&R Asphalt Overlay | 9/28/2004 | AC | 10 | 53,165 | 42 | $371,000 |
| 2027 | Rolle Airfield | A02RL | 10 | Major M&R Asphalt Reconstruction | 6/30/1992 | AC | 25 | 22,670 | 5 | $181,000 |
| 2027 | Ryan Field | RW1533RY | 10 | Major M&R Asphalt Overlay | 2/2/2000 | AC | 18 | 253,388 | 54 | $1,598,000 |
| 2027 | Ryan Field | TWB2RY | 10 | Major M&R Asphalt Overlay | 10/3/2014 | AC | 10 | 73,138 | 55 | $461,000 |
| 2027 | Ryan Field | TWBRY | 10 | Major M&R Asphalt Overlay | 6/1/2004 | AAC | 10 | 187,216 | 54 | $1,181,000 |
| 2027 | Ryan Field | TWDRY | 30 | Major M&R Asphalt Reconstruction | 6/1/1999 | AC | 24 | 49,197 | 21 | $474,000 |
| 2027 | Ryan Field | TWDRY | 40 | Major M&R Asphalt Reconstruction | 2/2/2000 | AC | 24 | 7,928 | 29 | $76,000 |
| 2027 | Ryan Field | TWERY | 10 | Major M&R Asphalt Overlay | 6/4/2004 | AC | 10 | 103,497 | 51 | $653,000 |
| 2027 | Safford Regional/1LT Duane Spalsbury Field | HP01SF | 10 | Major M&R PCC Reconstruction | 6/30/1998 | PCC | 27 | 5,293 | 28 | $214,000 |
| 2027 | Safford Regional/1LT Duane Spalsbury Field | HP01SF | 20 | Major M&R Asphalt Reconstruction | 6/30/1998 | AC | 27 | 23,621 | 13 | $303,000 |
| 2027 | Safford Regional/1LT Duane Spalsbury Field | TH01SF | 10 | Major M&R Asphalt Reconstruction | 6/1/1996 | AC | 27 | 30,516 | 37 | $391,000 |
| 2027 | Safford Regional/1LT Duane Spalsbury Field | TH01SF | 20 | Major M&R Asphalt Reconstruction | 6/1/1998 | AC | 27 | 32,289 | 15 | $414,000 |
| 2027 | Safford Regional/1LT Duane Spalsbury Field | TH01SF | 35 | Major M&R PCC Reconstruction | 2/1/2018 | PCC | 27 | 1,440 | 25 | $58,000 |
| 2027 | Safford Regional/1LT Duane Spalsbury Field | TWCSF | 10 | Major M&R Asphalt Reconstruction | 5/19/2005 | AAC | 24 | 215,117 | 32 | $2,757,000 |
| 2027 | San Carlos Apache | A01SA | 10 | Major M&R Asphalt Overlay | 12/4/2003 | AC | 14 | 155,007 | 48 | $1,193,000 |
| 2027 | San Carlos Apache | A02SA | 10 | Major M&R Asphalt Overlay | 6/3/2003 | AC | 14 | 161,054 | 48 | $1,240,000 |
| 2027 | San Carlos Apache | A02SA | 20 | Major M&R Asphalt Overlay | 8/3/2005 | AC | 14 | 44,186 | 54 | $340,000 |
| 2027 | San Carlos Apache | RW927SA | 10 | Major M&R Asphalt Overlay | 7/3/2016 | AAC | 6 | 658,942 | 51 | $5,073,000 |
| 2027 | San Carlos Apache | TWASA | 10 | Major M&R Asphalt Overlay | 10/4/1999 | AC | 10 | 121,810 | 54 | $938,000 |
| 2027 | Scottsdale | A01SC | 20 | Major M&R Asphalt Overlay | 7/30/2018 | AC | 14 | 217,440 | 49 | $1,725,000 |
| 2027 | Scottsdale | A01SC | 30 | Major M&R Asphalt Overlay | 3/2/2003 | AC | 14 | 154,524 | 40 | $1,226,000 |
| 2027 | Scottsdale | A01SC | 60 | Major M&R Asphalt Overlay | 3/15/2011 | AC | 14 | 292,911 | 49 | $2,324,000 |
| 2027 | Scottsdale | A01SC | 70 | Major M&R Asphalt Overlay | 3/15/2011 | AC | 14 | 238,094 | 54 | $1,889,000 |
| 2027 | Scottsdale | A01SC | 90 | Major M&R Asphalt Overlay | 6/6/2010 | AC | 14 | 17,718 | 40 | $141,000 |
| 2027 | Scottsdale | TH01SC | 10 | Major M&R Asphalt Overlay | 1/1/1997 | AC | 22 | 11,507 | 50 | $91,000 |
| 2027 | Scottsdale | TWASC | 30 | Major M&R Asphalt Overlay | 8/29/2003 | AAC | 10 | 17,050 | 48 | $135,000 |
| 2027 | Sedona | A01SD | 20 | Major M&R Asphalt Reconstruction | 1/3/2003 | AC | 25 | 62,345 | 27 | $664,000 |
| 2027 | Sedona | A02SD | 20 | Major M&R Asphalt Overlay | 6/3/2008 | AC | 14 | 58,600 | 46 | $409,000 |
| 2027 | Sedona | HP01SD | 10 | Major M&R Asphalt Reconstruction | 6/3/1988 | AC | 27 | 28,837 | 15 | $307,000 |
| 2027 | Sedona | TH01SD | 10 | Major M&R Asphalt Reconstruction | 2/4/1999 | AC | 27 | 86,740 | 29 | $923,000 |
| 2027 | Seligman | A01SG | 10 | Major M&R Asphalt Overlay | 1/3/1999 | AC | 14 | 81,109 | 47 | $566,000 |
| 2027 | Seligman | A01SG | 20 | Major M&R Asphalt Reconstruction | 8/3/2013 | AAC | 25 | 5,433 | 23 | $58,000 |
| 2027 | Sells | A01SE | 10 | Major M&R Asphalt Reconstruction | 6/1/1980 | AC | 25 | 5,745 | 0 | $55,000 |
| 2027 | Sells | RW422SE | 10 | Major M&R Asphalt Reconstruction | 6/1/1990 | AC | 23 | 356,790 | 22 | $3,435,000 |
| 2027 | Show Low Regional | ACENTRALSL | 10 | Major M&R Asphalt Overlay | 10/8/2004 | AAC | 14 | 335,660 | 47 | $2,121,000 |
| 2027 | Show Low Regional | ANORTHSL | 10 | Major M&R Asphalt Overlay | 1/1/1998 | AAC | 14 | 158,683 | 44 | $1,003,000 |
| 2027 | Show Low Regional | HP01SL | 10 | Major M&R Asphalt Reconstruction | 4/3/2006 | AC | 27 | 6,175 | 14 | $60,000 |
| 2027 | Show Low Regional | RW422SL | 10 | Major M&R Asphalt Overlay | 6/1/2001 | AAC | 18 | 236,320 | 55 | $1,493,000 |
| 2027 | Show Low Regional | TH01SL | 10 | Major M&R Asphalt Reconstruction | 6/1/1979 | AC | 27 | 3,660 | 2 | $35,000 |
| 2027 | Show Low Regional | TH01SL | 20 | Major M&R Asphalt Reconstruction | 6/3/2007 | AC | 27 | 76,310 | 35 | $736,000 |
| 2027 | Show Low Regional | TH01SL | 30 | Major M&R Asphalt Reconstruction | 6/1/2002 | AC | 27 | 17,852 | 31 | $172,000 |
| 2027 | Show Low Regional | TH01SL | 40 | Major M&R Asphalt Reconstruction | 1/1/2006 | AC | 27 | 66,750 | 31 | $644,000 |
| 2027 | Show Low Regional | TWA4SL | 10 | Major M&R Asphalt Reconstruction | 6/30/1998 | AAC | 24 | 36,913 | 9 | $356,000 |
| 2027 | Show Low Regional | TWBSL | 10 | Major M&R Asphalt Reconstruction | 1/1/1985 | AC | 24 | 95,678 | 0 | $923,000 |
| 2027 | Show Low Regional | TWDSL | 10 | Major M&R Asphalt Reconstruction | 10/1/2004 | AAC | 24 | 10,855 | 27 | $105,000 |
| 2027 | Sierra Vista Municipal-Libby Army Airfield | A01SV | 30 | Major M&R Asphalt Reconstruction | 10/3/2020 | AC | 25 | 77,031 | 40 | $914,000 |
| 2027 | Sierra Vista Municipal-Libby Army Airfield | AHOLD26SV | 10 | Major M&R Asphalt Reconstruction | 12/8/2005 | AAC | 25 | 45,230 | 14 | $537,000 |
| 2027 | Springerville Municipal | A01SP | 10 | Major M&R Asphalt Reconstruction | 6/1/1979 | AAC | 25 | 46,108 | 28 | $599,000 |
| 2027 | Springerville Municipal | A01SP | 20 | Major M&R Asphalt Overlay | 6/4/2007 | AC | 14 | 244,730 | 51 | $2,082,000 |
| 2027 | Springerville Municipal | A02SP | 10 | Major M&R Asphalt Reconstruction | 6/30/1988 | AC | 25 | 41,219 | 18 | $535,000 |
| 2027 | Springerville Municipal | RW1129SP | 10 | Major M&R Asphalt Overlay | 10/1/2002 | AAC | 18 | 282,835 | 53 | $2,406,000 |
| 2027 | Springerville Municipal | RW321SP | 20 | Major M&R Asphalt Reconstruction | 6/3/1993 | AC | 23 | 50,175 | 39 | $651,000 |
| 2027 | Springerville Municipal | TWBSP | 10 | Major M&R Asphalt Overlay | 6/4/2013 | AAC | 10 | 119,438 | 55 | $1,016,000 |
| 2027 | Springerville Municipal | TWBSP | 20 | Major M&R Asphalt Reconstruction | 6/2/1996 | AC | 24 | 6,282 | 27 | $82,000 |
| 2027 | St Johns Industrial Air Park | TH01SJ | 10 | Major M&R Asphalt Reconstruction | 6/4/2010 | AC | 27 | 16,887 | 28 | $219,000 |
| 2027 | St Johns Industrial Air Park | TWASJ | 10 | Major M&R Asphalt Reconstruction | 1/1/1985 | AC | 24 | 96,552 | 0 | $1,254,000 |
| 2027 | Taylor | TH01TA | 10 | Major M&R Asphalt Overlay | 6/3/2007 | AC | 22 | 35,303 | 52 | $223,000 |
| 2027 | Tombstone Municipal | TWATS | 10 | Major M&R Asphalt Reconstruction | 1/1/1980 | AC | 24 | 26,919 | 24 | $319,000 |
| 2027 | Tuba City | A01TC | 10 | Major M&R Asphalt Reconstruction | 1/1/1990 | AC | 25 | 61,253 | 20 | $717,000 |
| 2027 | Tuba City | RW1533TC | 10 | Major M&R Asphalt Reconstruction | 1/1/1990 | AC | 23 | 227,250 | 25 | $2,660,000 |
| 2027 | Tuba City | RW1533TC | 20 | Major M&R Asphalt Overlay | 7/3/2016 | AAC | 6 | 90,525 | 54 | $694,000 |
| 2027 | Tuba City | TWATC | 10 | Major M&R Asphalt Reconstruction | 1/1/1990 | AC | 24 | 33,464 | 23 | $392,000 |
| 2027 | Whiteriver | A01WH | 10 | Major M&R Asphalt Overlay | 6/3/2000 | AC | 14 | 127,322 | 51 | $805,000 |
| 2027 | Whiteriver | TWAWH | 10 | Major M&R Asphalt Overlay | 6/3/2000 | AC | 10 | 271,735 | 49 | $1,717,000 |
| 2027 | Wickenburg Municipal | TH01WK | 10 | Major M&R Asphalt Reconstruction | 7/30/2003 | AAC | 27 | 57,941 | 31 | $702,000 |
| 2027 | Wickenburg Municipal | TH01WK | 20 | Major M&R PCC Reconstruction | 4/12/2000 | PCC | 22 | 768 | 41 | $29,000 |
| 2027 | Wickenburg Municipal | TH01WK | 30 | Major M&R Asphalt Overlay | 10/3/2003 | AAC | 22 | 73,028 | 40 | $579,000 |
| 2027 | Window Rock | A01WR | 10 | Major M&R Asphalt Reconstruction | 1/1/1970 | AC | 25 | 87,529 | 6 | $1,137,000 |
| 2027 | Window Rock | A01WR | 20 | Major M&R Asphalt Reconstruction | 1/1/1970 | AC | 25 | 63,785 | 0 | $828,000 |
| 2027 | Window Rock | RW321WR | 10 | Major M&R Asphalt Reconstruction | 1/1/1980 | AAC | 23 | 326,250 | 8 | $4,236,000 |
| 2027 | Window Rock | TWAWR | 10 | Major M&R Asphalt Reconstruction | 1/1/1980 | AAC | 24 | 34,517 | 15 | $448,000 |
| 2027 | Window Rock | TWAWR | 20 | Major M&R Asphalt Reconstruction | 1/1/1970 | AC | 24 | 18,020 | 0 | $234,000 |
| 2027 | Winslow-Lindbergh Regional | A01WN | 10 | Major M&R Asphalt Reconstruction | 1/3/1980 | AC | 25 | 147,438 | 35 | $1,422,000 |
| 2027 | Winslow-Lindbergh Regional | A02WN | 10 | Major M&R Asphalt Reconstruction | 9/25/2003 | AC | 25 | 116,718 | 22 | $1,126,000 |
| 2027 | Winslow-Lindbergh Regional | A02WN | 20 | Major M&R PCC Reconstruction | 1/2/1996 | PCC | 25 | 13,977 | 21 | $426,000 |
| 2027 | Winslow-Lindbergh Regional | RW1129WN | 10 | Major M&R Asphalt Reconstruction | 1/1/1994 | AC | 26 | 532,621 | 22 | $5,137,000 |
| 2027 | Winslow-Lindbergh Regional | RW1129WN | 20 | Major M&R Asphalt Reconstruction | 1/1/1994 | AC | 26 | 532,501 | 32 | $5,136,000 |
| 2027 | Winslow-Lindbergh Regional | RW422WN | 20 | Major M&R Asphalt Reconstruction | 1/2/1983 | AC | 23 | 393,961 | 24 | $3,800,000 |
| 2027 | Winslow-Lindbergh Regional | TWDWN | 10 | Major M&R Asphalt Reconstruction | 1/2/1973 | AC | 24 | 20,426 | 28 | $197,000 |
| 2027 | Winslow-Lindbergh Regional | TWDWN | 20 | Major M&R PCC Reconstruction | 1/1/1973 | PCC | 24 | 19,471 | 26 | $594,000 |
| 2027 | Yuma International | ADCCYM | 010 | Major M&R PCC Reconstruction | 1/1/1975 | PCC | 12 | 92,250 | 62 | $2,333,000 |
| 2027 | Yuma International | ADCCYM | 090 | Major M&R Asphalt Reconstruction | 6/1/2009 | AC | 25 | 29,220 | 37 | $234,000 |
| 2027 | Yuma International | ADCCYM | 110 | Major M&R Asphalt Reconstruction | 6/5/2008 | AC | 25 | 9,650 | 33 | $77,000 |
| 2027 | Yuma International | APAPPYYM | 10 | Major M&R Asphalt Overlay | 6/5/2007 | AC | 14 | 118,786 | 52 | $623,000 |
| 2027 | Yuma International | APAPPYYM | 20 | Major M&R PCC Reconstruction | 6/1/2011 | PCC | 12 | 3,000 | 64 | $76,000 |
| 2027 | Yuma International | ATERMYM | 10 | Major M&R Asphalt Reconstruction | 6/2/2010 | AC | 25 | 96,049 | 36 | $768,000 |
| 2027 | Yuma International | ATERMYM | 30 | Major M&R Asphalt Overlay | 6/2/2010 | AC | 14 | 77,319 | 52 | $405,000 |
| 2027 | Yuma International | HP01YM | 10 | Major M&R PCC Reconstruction | 1/1/1981 | PCC | 27 | 1,805 | 4 | $46,000 |
| 2027 | Yuma International | HP02YM | 10 | Major M&R PCC Reconstruction | 1/1/1995 | PCC | 21 | 800 | 62 | $20,000 |
| 2027 | Yuma International | HP03YM | 10 | Major M&R PCC Reconstruction | 6/1/2010 | PCC | 27 | 800 | 5 | $20,000 |
| 2027 | Yuma International | TWTERMYM | 10 | Major M&R PCC Reconstruction | 6/1/1987 | PCC | 10 | 9,580 | 44 | $242,000 |
| Total Estimated Cost for 2027: | $547,465,000 | |||||||||
| 2028 | Benson Municipal/Paul Kerchum Field | AFUELBN | 10 | Major M&R PCC Reconstruction | 6/2/2021 | PCC | 12 | 5,253 | 65 | $209,000 |
| 2028 | Falcon Field | TWEMF | 20 | Major M&R Asphalt Overlay | 8/22/2012 | AC | 8 | 20,439 | 54 | $172,000 |
| 2028 | Lake Havasu City | A01LH | 30 | Major M&R PCC Reconstruction | 1/1/2003 | PCC | 12 | 1,600 | 65 | $66,000 |
| 2028 | Mesa Gateway | TWEWG | 10 | Major M&R PCC Reconstruction | 6/1/2007 | PCC | 8 | 19,732 | 65 | $801,000 |
| 2028 | Prescott Regional/Ernest A Love Field | ASOUTHPR | 50 | Major M&R PCC Reconstruction | 6/1/2007 | PCC | 12 | 720 | 65 | $26,000 |
| 2028 | Yuma International | ATERMYM | 20 | Major M&R PCC Reconstruction | 1/3/1987 | PCC | 12 | 211,031 | 65 | $5,656,000 |
| Total Estimated Cost for 2028: | $6,930,000 | |||||||||
| 2029 | Cochise County | A01CO | 10 | Major M&R PCC Reconstruction | 6/30/1992 | PCC | 12 | 16,177 | 64 | $682,000 |
| 2029 | Nogales International | A01NG | 40 | Major M&R PCC Reconstruction | 6/2/1999 | PCC | 12 | 21,939 | 65 | $835,000 |
| 2029 | Page Municipal | RW1634PM | 10 | Major M&R Asphalt Overlay | 11/3/2013 | AAC | 4 | 784,920 | 54 | $6,763,000 |
| 2029 | Page Municipal | RW1634PM | 30 | Major M&R Asphalt Overlay | 11/3/2013 | AAC | 4 | 42,882 | 54 | $370,000 |
| 2029 | Prescott Regional/Ernest A Love Field | TH02PR | 30 | Major M&R PCC Reconstruction | 7/1/2000 | PCC | 21 | 11,500 | 65 | $435,000 |
| 2029 | Sedona | HP01SD | 20 | Major M&R PCC Reconstruction | 6/3/1997 | PCC | 21 | 9,600 | 63 | $363,000 |
| Total Estimated Cost for 2029: | $9,448,000 | |||||||||
| 2030 | Marana Regional | RW1230AV | 10 | Major M&R Asphalt Overlay | 4/3/2016 | AAC | 4 | 707,814 | 53 | $5,318,000 |
| 2030 | Payson | HP02PY | 10 | Major M&R PCC Reconstruction | 6/2/2015 | PCC | 19 | 5,468 | 65 | $242,000 |
| 2030 | Yuma International | TWH1YM | 30 | Major M&R PCC Reconstruction | 6/5/2007 | PCC | 8 | 59,564 | 65 | $1,794,000 |
| Total Estimated Cost for 2030: | $7,354,000 | |||||||||
| 2031 | Falcon Field | TH01MF | 10 | Major M&R Asphalt Overlay | 6/30/2000 | AC | 21 | 1,553,682 | 54 | $15,561,000 |
| 2031 | Payson | RW624PY | 10 | Major M&R Asphalt Overlay | 7/2/2015 | AAC | 4 | 445,720 | 53 | $4,332,000 |
| 2031 | Rolle Airfield | HP01RL | 10 | Major M&R PCC Reconstruction | 6/2/1993 | PCC | 19 | 400 | 65 | $13,000 |
| 2031 | Springerville Municipal | HP01SP | 10 | Major M&R PCC Reconstruction | 6/1/2007 | PCC | 19 | 1,202 | 64 | $62,000 |
| Total Estimated Cost for 2031: | $19,968,000 | |||||||||
| 2032 | Benson Municipal/Paul Kerchum Field | TWABN | 10 | Major M&R Asphalt Overlay | 1/1/2003 | AC | 8 | 201,579 | 55 | $2,097,000 |
| 2032 | Taylor | TWATA | 10 | Major M&R Asphalt Overlay | 8/3/2013 | AAC | 8 | 90,257 | 54 | $763,000 |
| 2032 | Taylor | TWATA | 20 | Major M&R Asphalt Overlay | 1/2/2006 | AC | 8 | 206,977 | 53 | $1,750,000 |
| 2032 | Yuma International | ADCCYM | 040 | Major M&R PCC Reconstruction | 1/1/1979 | PCC | 12 | 28,931 | 64 | $979,000 |
| Total Estimated Cost for 2032: | $5,589,000 | |||||||||
| 2033 | Kingman | TWCKG | 20 | Major M&R PCC Reconstruction | 6/1/1940 | PCC | 7 | 61,950 | 65 | $3,405,000 |
| 2033 | Safford Regional/1LT Duane Spalsbury Field | A01SF | 10 | Major M&R Asphalt Overlay | 1/2/2014 | AC | 12 | 442,138 | 54 | $5,266,000 |
| 2033 | Sedona | HP02SD | 10 | Major M&R PCC Reconstruction | 6/3/1997 | PCC | 19 | 10,000 | 63 | $477,000 |
| Total Estimated Cost for 2033: | $9,148,000 | |||||||||
| Total Estimated Cost for 2034: | $0 | |||||||||
| Total Estimated Cost for 2027-2034: | $605,902,000 | |||||||||